McNeil Canyon Road Realignment

County Road Project #988

  • Project Number: County Road Project (CRP) 988
  • Project Length: Milepost 1.64 - 2.78 (Approx. One Mile)
  • Construction Schedule: Anticipated construction in 2025
  • Last Updated: August 30, 2023

Vicinity Map

988_VicinityMap

Project Description

This project will re-route a section of McNeil Canyon Rd north of its existing alignment. The new segment will create a much safer road with appropriate sight distance, the elimination of a dangerous curves, and a reduced grade to 9.4%. Douglas County proposes the placement of 8-inches of crushed surfacing base course, 4-inches of crushed surfacing top course, and 3-inches of hot mix asphalt with a surface width of 30-feet. The new roadway will consist of 11-foot travel lanes with 4-foot shoulders, along with additional lane widening through the 2,000-foot horizontal curves. Vertical and horizontal alignment will be resolved at substandard locations bringing them up to compliance with AASHTO standards for a 50 mph paved, rural roadway. Guardrail to be installed where appropriate.

Phase & Schedule

This project is currently in the Design Phase and scheduled for construction in 2025. 

1. Preliminary Engineering: Preliminary Engineering to be complete at the end of February 2025.

2. Right-of-Way Acquisition: Anticipated for completion April 2025.

3. Construction: Anticipated to begin in early April of 2025. 


Project Funding

This project is funded through the County Road Administration Board's (CRAB) Rural Arterial Program (RAP). The initial RATA funding was approved in 2022 in the amount of $2,653,200.





DJI_0048
  1. Traffic Impact
  2. Bidding & Contract Information
  3. Plan Holders

The road will be reduced to alternating one-way traffic throughout construction. Please allow for extra travel time during this period. 

McNeil Canyon Road Realignment

  1. 1 10
  2. 2 11
  3. 3 12
  4. 4 1
  5. 5 2
  6. 6 3
  7. 7 4
  8. 8 5
  9. 9 6
  10. 10 7
  11. 11 8
  12. 12 9

Project Updates

10/01/2025 - Construction activity progress and updates associated with McNeil Canyon Road Realignment project for the week of October 1st through October 10th area as follows:

  • Final grading of crushed surfacing.
  • Final installation of drainage rock.
  • Installation of erosion control measures.
  • Paving to begin Monday October 6, 2025.

Traffic impacts:

  • Speed limits throughout the work zone will be reduced to 25 MPH.
  • Flagger controlled alternating one-way traffic patterns through the work zone will be in effect during working hours of 7:00 am -4:30 pm Monday through Friday.
  •  Expected wait time up to 15 minutes.
  •  Roadway will be open to two-way traffic during non-working hours. 

09/15/2025 - Construction activity progress and updates associated with the McNeil Canyon Road Realignment project for the week of September 15th through September 19th are as follows:

  • Installation of crushed surfacing.
  • Excavation of drainage channels and ditches.
  • Excavation of driveways.

Traffic impacts:

  • Speed limits throughout the work zone will be reduced to 25 MPH.
  • Flagger controlled alternating one-way traffic patterns through the work zone will be in effect during working hours of 6:00 am -4:30 pm Monday through Friday.
  •  Expected wait time up to 15 minutes.
  •  Roadway will be open to two-way traffic during non-working hours. 

09/08/2025 - Construction activity progress and updates associated with the McNeil Canyon Road Realignment project for the week of September 8th through September 12th are as follows: 

  • Work resumed as of Monday September 8, 2025. 

08/05/2025 - Construction activity progress and updates associated with the McNeil Canyon Road Realignment project for the week of August 4th through August 8th are as follows:

  • Roadway excavation and embankment compaction.
  • Installation of rock for drainage channels.
  • Installation of culverts.
  • Installation of crushed surfacing rock.

Traffic impacts:

  • Speed limits throughout the work zone will be reduced to 25 MPH.
  • Flagger controlled alternating one-way traffic patterns through the work zone will be in effect during working hours of 6:00 am -4:30 pm Monday through Friday.
  •  Expected wait time up to 15 minutes.
  •  Roadway will be open to two-way traffic during non-working hours. 

07/30/2025 - Construction activity progress and updates associated with the McNeil Canyon Road Realignment project for the week of July 28th through August 1st are as follows:

  • Continued roadway excavation and embankment compaction.
  • Installation of rock for drainage channels.
  • Installation of culverts.
  • Shift to the new alignment beginning July 31st. 

Traffic impacts:

  • Speed limits throughout the work zone will be reduced to 25 MPH.
  • Flagger controlled alternating one-way traffic patterns through the work zone will be in effect during working hours of 6:00 am -4:30 pm Monday through Friday.
  •  Expected wait time up to 15 minutes.
  •  Roadway will be open to two-way traffic during non-working hours. 

07/22/2025 - Construction activity progress and updates associated with the McNeil Canyon Road Realignment project for the week of July 21st through July 25th are as follows:

  • Roadway excavation and embankment compaction.
  • Excavation of infiltration ponds and drainage ditches.
  • Clearing and grubbing of existing vegetation.

Traffic impacts:

  • Speed limits throughout the work zone will be reduced to 25 MPH.
  • Flagger controlled alternating one-way traffic patterns through the work zone will be in effect during working hours of 6:00 am -4:30 pm Monday through Friday.
  •  Expected wait time up to 15 minutes.
  •  Roadway will be open to two-way traffic during non-working hours. 

07/14/2025 - Construction activity progress and updates associated with the McNeil Canyon Road Realignment project for the week of July 14th through July 18th are as follows:

  • Asphalt removal on the existing McNeil Canyon Rd.
  • Roadway excavation and embankment compaction.
  • Excavation of infiltration ponds and drainage ditches.

Traffic impacts:

  • Speed limits throughout the work zone will be reduced to 25 MPH.
  • Flagger controlled alternating one-way traffic patterns through the work zone will be in effect during working hours of 6:00 am -4:30 pm Monday through Friday.
  •  Expected wait time up to 15 minutes.
  •  Roadway will be open to two-way traffic during non-working hours. 

07/07/2025 - Construction activity progress and updates associated with the McNeil Canyon Road Realignment project for the week of July 7th through July 11th are as follows:

  • Asphalt removal on the existing McNeil Canyon Rd.
  • Removal of guardrail.
  • Roadway excavation and embankment compaction.
  • Excavation of infiltration ponds. 

Traffic impacts:

  • Speed limits throughout the work zone will be reduced to 25 MPH.
  • Flagger controlled alternating one-way traffic patterns through the work zone will be in effect during working hours of 6:00 am -4:30 pm Monday through Friday.
  •  Expected wait time up to 10 minutes.
  •  Roadway will be open to two-way traffic during non-working hours. 

07/01/2025 - Construction activity progress and updates associated with the McNeil Canyon Road Realignment project for the week of June 30th through July 4th are as follows:

  • Roadway excavation and embankment construction.
  • Excavation of infiltration ponds.

Traffic impacts – There are no impacts to traffic currently. One way traffic will begin next week on 7/7. 

06/23/2025 - Construction activity progress and updates associated with the McNeil Canyon Road Realignment project for the week of June 23rd through June 27th are as follows:

  • Roadway excavation and embankment construction.
  • Excavation of infiltration ponds.
  • Installation of 60-inch culvert.

Traffic impacts – There are no impacts to traffic currently.

06/16/2025 - Construction activity progress and updates associated with the McNeil Canyon Road Realignment project for the week of June 16th through June 20th are as follows:

  • Roadway excavation and embankment construction.
  • Excavation of infiltration ponds.

Traffic impacts – There are no impacts to traffic currently.

06/09/2025 2025 – Construction activity progress and updates associated with the McNeil Canyon Road Realignment project for the week of June 9th through June 13th are as follows:

  • Continued mobilization of equipment.
  • Clearing and removal of existing vegetation.
  • Excavation of infiltration ponds.
  • Installation of culvert pipe.

Traffic impacts – There are no impacts to traffic currently.

06/02/2025 – Construction activity progress and updates associated with the McNeil Canyon Road Realignment project for the week of June 2nd through June 6th are as follows:

  • On site mobilization of equipment and personnel has begun. 
  • Silt fence installation. 
  • Start of roadway survey. 

FAQ's

  1. Will local residents have access to McNeil Canyon Hill during the project?
    1. The road will remain open to traffic during construction. However, expect delays on McNeil Canyon Road as the road will reduce to one way.
  2. When should we expect construction to be completed?
    1. We anticipate for construction to be complete November of 2025.
  3. Will there be any impacts to private roads such as Ridge Road?
    1. Ridge Road will remain open during construction; the entrance and first 80 ft. will be regraded and repaved. 
  4. At what hours of the day will there be closures and restrictions?
    1. The road will remain open but you can expect delays as the road will reduce to alternating one-way traffic.