Feil Place Canal Crossing

Last Updated: September 14, 2017


Bid Range - $100,000 - $200,000

 

* Note * Upon downloading these documents, please contact Carol Hardie at 509.888.6570, or email your Company Name, Address, Phone and Fax Numbers, Email (if different than sending email), and a Contact Person Name, to chardie@co.douglas.wa.us in order to be placed on the plan holders list.  This will enable us to forward addendums to you.

Vicinity Map

Vicinity Map

 

Project Data
Project Number: County Road Project 946
Project Length: 150 Lineal Feet
Construction Start: Oct 2017
 
Project Description

This contract provides for the improvement of “Feil Place Canal Crossing” consisting of removing existing wooden bridge, removing concrete canal liner, sawcut existing pavement/concrete, roadway excavation and embankment, precast reinforced concrete box culvert, crushed surfacing, HMA, seeding, fertilizing and mulching, project temporary traffic control and other work, all in accordance with the attached Contract Plans, these Contract Provisions, and the Standard Specifications.


Project Status
Project will be advertised on September 7, 2017.

Traffic Impacts

Road will be closed during construction. 



For more information on this project contact Douglas County Transportation at (509) 884-7173.