2017 County Wide Crushing

Last Updated: March 23, 2017


* Note * Upon downloading these documents, please contact Carol Hardie at 509.888.6570, or email your Company Name, Address, Phone and Fax Numbers, Email (if different than sending email), and a Contact Person Name, to chardie@co.douglas.wa.us in order to be placed on the plan holders list.  This will enable us to forward addendums to you.

Vicinity Map - Pit 106

holcomb2

Vicinity Maps

 

Project Data
Project Number: ER17
Project Length: N/A
Construction Start: Spring 2017
 
Project Description

The proposed work to be performed under this contract consists of crushing and stockpiling at Holcomb Pit and Pit 106 for a total of 110,000 tons as follows:

  • Crush 55,000 tons of Maintenance Top Course, 35,000 tons of Crushed Surfacing Base Course, and 20,000 tons of Crushed Screening ½ inch – No.4.

Project Status

The project will be advertised for bids on March 23, 2017.


Traffic Impacts

None



For more information on this project contact Douglas County Transportation at (509) 884-7173.